Pipeline Project - 2017

 

PetroleumTerminal.com

 

 

 

 

 

 

 

One third mile, clean petroleum

products PL project, covering

 3  construction sites.

   

 

Week 1

   PREP WORK

All images

captured with

 iPhone 7

 

PARKING LOT:  Steel pipe layout in prep for HDD "pull".

 

   
 

 

   

22" O.D. HDPE casing prior to startup of project. 

   
 

 

PARKING LOT:  Carefully removing dirt around underground pipes.

Week 2 

   TRENCHING PIPELINE FROM CONTAINER YARD

 

 

 

 

CONTAINER YARD:  Aerial from drone.

   

 

 

 

 

CONTAINER YARD:  Trenching operation.

   

 

 

 

 

CONTAINER YARD:  Trenching  to above ground manifold.

   
 

 

CONTAINER YARD:  Ready to install pipe. 

   
 

 

CONTAINER YARD:  Laying out pipe in trench to manifold.

Week 3 

    MANIFOLD WORK

 

 

 

 

 

ABOVE GROUND MANIFOLD:  Pour concrete to support valves & piping.

   
 

 

ABOVE GROUND MANIFOLD:  Pipeline work under street.

Week 4 

    HDD IN PARKING LOT

 

 

PARKING LOT:  Drone view pulling pipeline thru casing.

   

 

 

CONTAINER YARD:  Ditch Witch drilling bore hole.

   
 

 

PARKING LOT:  Fusing HDPE Pipe.

   
 

 

PARKING LOT:  Reaming: 12", 20" 33" after successful initial boring.

   
 

 

PARKING LOT:  HDPE Pipe lined up for "pull".

   
 

 

PARKING LOT:  HDPE pipe final adjustments.

   
 

Dakota Access Pipeline.  (File Photo - For comparison purposes only.)

   

 

Compare the terrain, the obstacles, the congestion, the potential

danger to health and environment.  Compared to the pipeline

illustrated, the Dakota Access is a piece-of-cake. 

   
 

 

CONTAINER YARD:  Ditch Witch pulls 22" HDPE casing thru bore hole.

Week 5 

  

 

 

PARKING LOT:  Getting ready to pig the casing.

   
 

 

PARKING LOT:  Connecting to Underground Vault.

   
 

 

CONTAINER YARD: PL ready to be slurried.

   
 

 

ABOVE GROUND MANIFOLD:  Instrumentation pad ready to be poured.

   
 

 

CONTAINER YARD:  Pouring slurry in trench.

Wk 6

  

 

 

CONTAINER YARD:  Tying in bore PL to PL to manifold.

   
 

 

CONTAINER YARD:  Ready for slurry.

   
 

 

PARKING LOT:  No shortage of pipes to avoid.

Week 8

  

 

 

PARKING LOT:  Boot & PL routed thru pipes.

   
 

 

PARKING LOT:  Casing for future rail spur.

   
 

 

ABOVE GROUND MANIFOLD:  manifold placement on pad.

   
 

 

ABOVE GROUND MANIFOLD:  Cutting into 20" pipeline.

   
 

 

ABOVE GROUND MANIFOLD:  Shoring & Prep.

   
 

 

ABOVE GROUND MANIFOLD:  Lining up east leg.

   
 

 

ABOVE GROUND MANIFOLD:  Connecting Pipelines.

Final 

  

 

 

ABOVE GROUND MANIFOLD:  Sand blasted and coated.

 

07/18/17